Scheduled maintenance for Visma.net ERP - Data center migration
Scheduled Maintenance Report for Visma Cloud Services
Completed
As of today, 26.07.2020 12:00 CEST Production environment is online in AWS.
We have monitored the application, logs and the performance and everything looks ok. We will continue to closely monitor the application tomorrow and the following days.
Posted Jul 26, 2020 - 20:24 CEST
Update
Visma.net ERP is working as expected, we did not encountered any issues.
We will continue to monitor the application and the performance.
Posted Jul 26, 2020 - 14:01 CEST
Update
Visma.net ERP is now online for all customers and partners.
We will continue to closely monitor the application and the performance. We expect a peak in activity when we switch the environment live. This is according to plan.
Posted Jul 26, 2020 - 12:00 CEST
Verifying
We have now moved all customers, demo and test databases to AWS. Currently, we are verifying all systems configurations. In addition we are monitoring and verifying logs for our test companies used for this data center migration.

Today, 26.07.2020, at 12:00 CEST we will open up Visma.net ERP to all customers and partners. This is before the maintenance window is completed.

We will continue to monitor and follow up. We expect a peak in activity when we switch the environment live. This is according to plan.
Posted Jul 26, 2020 - 00:51 CEST
Update
Tests results of main functionality and integrations shows that everything is ok. Application and all services are running as expected.
Continuing the migration of databases.
We will provide and update no later than midnight.
Posted Jul 25, 2020 - 18:31 CEST
In progress
Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted Jul 25, 2020 - 12:00 CEST
Scheduled
As part of our continuous commitment to provide better services and more robust hosting experience to our users, Visma will be carrying out a major data center migration from Visma IT & Communications (DigiPlex Norway Rosenholm & Ulven) to Amazon Data Center (AWS Stockholm region) on July 25, 2020.

The data center migration has been planned to take place starting on Saturday 25th of July at 12:00 CEST until Sunday 26th of July at 23:59 CEST. A downtime is to be expected during the migration.
Posted Jul 08, 2020 - 12:38 CEST
This scheduled maintenance affected: Visma Net (Visma Net, Visma Net API).