Flyt - Firewall migration from Checkpoint to Palo Alto - NHN

Scheduled Maintenance Report for Visma Cloud Services

Completed

The scheduled maintenance has been completed.
Posted Nov 03, 2023 - 01:00 CET

In progress

Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted Nov 02, 2023 - 23:00 CET

Scheduled

Datacenter Network Team will continue with the migrations that are part of the Task 402 Firewall migration, by migrating the Virtual Firewall that is used by NHN, from Checkpoint to Palo Alto. Downtime is expected during the maintenance on all Flyt NHN services.
Posted Oct 27, 2023 - 16:32 CEST
This scheduled maintenance affected: Flyt Welfare & Health (Visma Flyt PPT, Visma Flyt BVV, Visma Flyt Helse, Visma Flyt Sikker Sak, Flyt Barnevern).